Request a Building Control site visit

A formal notification of a Building Notice or a Full Plans application needs to be deposited with the Council's Building Control Section before a visit can be made.

Request a site visit

Request an inspection

Inspections can be booked two working days in advance, for Monday to Friday only. No visits are available at weekends. Please use our site visit application form to request an inspection. If you have any questions or comments, please contact the Building Control Team.

It is not possible to book specific times for a Building Surveyor to attend site.

You must give notice two days before commencement of works.

Inspection Framework - Owner/Occupier/Builder

The following inspection stages are those for which the Regulations require that the builder or owner give formal “notice” before covering the work in question. Inspections will need to be made as appropriate to the job in question. In most instances 1 days notice is required, occupation and completion inspections require 5 days notice.

As a general rule however, provided a request is made for any inspection before 10.00am on work days, an inspection will normally be made the same day. A request at any other time will normally involve an inspection the following working day.

“Notice” referred to above can be by telephone directly to the Building Control Surveyor supervising your project, or Building Control Admin support Team on 020 8891 7117, or fax on 020 8891 7347, or email to: buildingcontrol@richmond.gov.uk

Statutory inspections
Type of Works Description Notice Notes
Commencement
of works
That you intend to commence works 2 days This might include site of existing foundation examination
Foundation excavations Before anything is placed in the excavations 1 day More than one visit may be necessary
Covering of
foundations
Before the foundation concrete is covered 1 day May be done with either of the next two inspections
Hardcore
Oversite
Before any hardcore or concrete laid over the site is covered 1 day May include mesh reinforcement, thermal insulation provision and damp proof membrane
Damp
Proof
Courses
Before any damp proof course or membrane is covered, including tanking 1 day May be combined with above inspection, but may include dpc's in other locations
Drains Before covering up any drain or sewer 1 day Includes all access, cleaning and rodding points
Backfilling
drain
excavations
Before backfilling any drain or sewer which has been haunched or covered 5 days At this stage it may be prudent to include a test on the underground drains
Occupation Before a building or any part of it is occupied 5 days Occupying a building before substantial completion may give rise to health and safety risks.  A plumbing test may be included
Completion After completion of the works 5 days No Completion Certificate will be issued without a final inspection and notice of completion
Important:
Part P
Electrical
Safety
Installation 1 day All electrical work required to meet the Requirements of Part P (Electrical Safety) must be designed, installed, inspected and tested by a person competent to do so.
Completion 5 days Prior to completion the Council should be satisfied that Part P has been complied with.  This may require an appropriate BS7671 electrical installation certificate to be issued for the work by a person competent to do so.

In addition to the "statutory inspections" referred to above, as appropriate to the project and with specific reference to this particular project the following items should be inspected also:

Additional Inspections

  • IL03 - Steel/Timber beams
  • IL01 - Thermal insulation

You are therefore advised to ensure that notice is given so that these items are particularly inspected.  It must be understood that this list is not comprehensive, but highlights items of particular and specific interest to a project.

In this section:

Updated: 15 December 2016